Adams & Columbus road resurfacing

Event Date: 
Tuesday, September 7, 2021 (All day) to Saturday, September 11, 2021 (All day)

Road prep work on Adams Street and Columbus Road will begin on Wednesday 9/1 and 9/2.

Road grinding will begin on Tuesday 9/7 and if all goes well, we will have the base coat done by Saturday, 9/11.

We hope to have this paving project done by 9/24.

Residents that have irrigation systems near the roadside edge (in the right-of-way) need to be flagged to avoid possible damage. The town is not responsible for any damage to items in the right of way.

As always, The Highway Department appreciates your patience and understanding during these weeks of construction.